logo
Hongkong Yaning Purification industrial Co.,Limited violaquan@dgync.com 86--18373128025
Hongkong Yaning Purification industrial Co.,Limited نمایه شرکت
اخبار
صفحه اصلی > اخبار >
اخبار شرکت در مورد Turnkey Cleanroom Project Delivery: How YANING Equipped a GMP Pharmaceutical Facility in 45 Days

Turnkey Cleanroom Project Delivery: How YANING Equipped a GMP Pharmaceutical Facility in 45 Days

2026-10-10
Latest company news about Turnkey Cleanroom Project Delivery: How YANING Equipped a GMP Pharmaceutical Facility in 45 Days

From Layout to Validation: A Complete GMP Cleanroom Project in 45 Days

When a pharmaceutical manufacturer needed a new GMP-grade filling area, the challenge was not simply purchasing equipment — it was delivering a fully validated cleanroom on a tight schedule. This case study follows a turnkey cleanroom project delivered by YANING (FFU Cleanroom), from the first site survey to the final particle-count test.

Project Brief

  • Application: pharmaceutical filling and packaging area
  • Target standard: ISO Class 7 / Grade C cleanroom
  • Scope: design, equipment supply, installation guidance and commissioning
  • Timeline: 45 days from order confirmation to validation

Phase 1 — Layout and Airflow Design

The project began with airflow modelling. Engineers defined a positive-pressure cascade so that air moves from the cleanest zones toward less clean areas, with laminar flow over critical filling stations and controlled air-change rates throughout the room. Getting this right at the design stage avoided costly changes later, when equipment is already on site.

Phase 2 — Equipment Supply

YANING supplied a complete equipment package: cleanroom air showers at personnel entry to remove surface particles; dynamic pass boxes with electronic interlocking for safe material transfer; FFU fan filter units and HEPA filter terminal boxes to deliver filtered air; and stainless steel cleanroom furniture for gowning and storage. Because every component came from a single manufacturer, the interfaces matched and installation was straightforward.

Phase 3 — Installation and Commissioning

Because the modules were prefabricated in the factory, onsite work was fast and predictable. Installation of the air showers, pass boxes and ceiling filtration systems was completed with minimal disruption to adjacent production lines, keeping the customer’s wider operations running throughout the project.

Phase 4 — Validation

The finished cleanroom was validated against the customer’s GMP requirements:

Parameter Target Result
Particle count (≥0.5 µm) ISO Class 7 Passed
Air change rate ≥25 air changes/hour Passed
Pressure differential +10 Pa vs. adjacent area Passed

Results

The cleanroom passed validation on the first attempt and was handed over within the 45-day schedule. The customer gained a compliant production area with no rework and no delay to product launch.

Lessons for Buyers Planning a Cleanroom

  • Engage the equipment supplier early so the airflow design and product selection are aligned.
  • Prefer factory-prefabricated, single-source systems to reduce interface risk onsite.
  • Plan validation from the start — the target class determines every equipment choice.
  • Choose a partner who stays accountable through commissioning, not just supply.

This project illustrates what a genuinely turnkey cleanroom partner can deliver: one point of responsibility, coordinated design, and equipment that works together from day one.

مناسبت ها
تماس ها
تماس ها: Miss. Viola
فکس: 86-0769-85419534
اکنون تماس بگیرید
به ما ایمیل بزنید